| Activity ID ▲▼ |
Activity Description ▲▼ |
WBS ▲▼ |
Cost Code ▲▼ |
Discipline ▲▼ |
Duration (d) ▲▼ |
Start Date ▲▼ |
Finish Date ▲▼ |
BAC ($USD) ▲▼ |
Earned Value ($) ▲▼ |
Progress % ▲▼ |
Total Float ▲▼ |
Critical Status |
Hierarchical WBS 1.0 to 7.0 Rollup Analysis ($360.0M Total BAC)
Decree 15/2021/ND-CP & Singapore BCA IDD Compliant
Building and Construction Industry Security of Payment Act (SOPA 2004) Monthly IPC Ledger (41 Periods)
Statutory 21-Day Payment Response Clock • 5% Retention Escrow Cap: $18.00M
| IPC # |
Claim Period |
Gross Certified ($M) |
5% Retention Withheld ($M) |
Net SOPA Claim ($M) |
Cumulative Outflow ($M) |
% Project Spend |
Statutory Response Deadline |
SOPA Certification Status |
Budget At Completion (BAC)
$360.00M
Baseline Capital Expenditure
Earned Value (EV)
$0.00M
0.0% Physical Complete
Actual Cost (AC)
$0.00M
Invoiced & Materials on Site
Cost Performance Index (CPI)
0.98
Cost Efficiency Factor (EV / AC)
Schedule Performance Index (SPI)
0.99
-4d Calendar Variance
Estimate At Completion (EAC)
$365.85M
Forecast Total Outturn Cost
Variance At Completion (VAC)
-$5.85M
Absorbed by Contingency Buffer
TCPI (To-Complete to EAC)
0.986
Required Performance Trajectory
Contingency Reserve Pool ($28.80M Baseline Allocation / 8.0% BAC)
Net Uncommitted Buffer: $22.95M (79.7%)
Committed to Cost Overrun (VAC): $5.85M
Unforeseen Subsurface: $9.00M | OFCI Currency/Tariff: $12.60M | Tier III Cx: $7.20M
Registered Variations & Scope Change Orders (Approved Log)
| CO ID |
Change Order Title |
Affected Package |
Cost Impact ($USD) |
Schedule Impact |
Approval Status |
Authorized Authority |